Hitz:Tianjin City, China Waste Incineration Power Plant: Mid-Zhu No-Beng-Hui-Heng

Hitz: Tianjin City, China Waste Incineration Power Plant: Mid-Zhu No-Beng-Hui-Heng

Hitachi Zosen Corporation

We received an order for incinerator construction work for a waste incineration power plant (Stoker type incinerator: 800 tons / day x 3 furnaces, power generation output: 40 MW x 2) from Mid-Heng No. (Tianjin) Environmental Reserve Co., Ltd. (Tianjin)

Waste Incineration Power Plant: Overview

Design and supply of grate, which is the main equipment of the waste incineration power plant,

We perform SV dispatch (technical instruction) work at the time of installation and trial operation.

China: Delivery record

In 2006, we received the first order for a waste incineration power plant in Chengdu, China.

Since then, we have received 25 orders in China.

A total of 135 orders received, including licensees’ results.

China Plant: Total Waste Disposal

The total amount of waste processed in China by waste incineration and power generation facilities supplied by the Company and licensee is approximately 138,500 tons / day.

The total power output was about 3,000 MW.

It greatly contributes to waste disposal and power supply in China.

Summary of this time:

1. Purchaser: Zhongzhi Noh (Tianjin) Environmental Reserve Source Co., Ltd. (Tianjin City)

2. Construction name: Construction work of the Tianjin Toei waste incineration power generation plant

3. Our company work: Design related to incinerators such as grate, supply of equipment, SV dispatching work at installation and trial operation etc.

4. Facility scale: Stoker type incinerator (800 tons / day × 3 furnaces), power generation output: 40 MW × 2

5. Construction site: Dongli District, Tianjin City, China

6. Completion date: March 2021