Thailand high-speed railway:  the first section, 40% of the total – completion in June 2019

Pakchon-Kulandong Station and Pan Asoke station (JETRO)

Thailand high-speed railway:  the first section, 40% of the total – completion in June 2019

Bangkok

March 4, 2019

Phase 1 of high-speed railway construction:

The first high-speed railway in Thailand (constructed in cooperation with Thailand and China), the progress rate in the first section is 40% of the total.

It was revealed at the interview with the construction company that the completion is expected to be around June 2019 slightly later than scheduled (February 21)

Thailand – China High Speed Rail Project:

Phase 1 construction:

Beginning in Bangkok – Northeast Nakorn Ratchasima County (about 260 km) on December 21, 2017 (see the article on January 11, 2018)

First section:

Construction of about 3.5 kilometer section of Pakchon-Kulandong Station and Pan Asoke station in the same prefecture is proceeding.

– JETRO