NEC / OLL:海底光缆/ MIST合同:亚洲连接8,100km
2020年8月21日
NEC ・东方链接私人有限公司:
NEC和OLL(* 1)签订了大容量海底光缆敷设项目“ MIST”的系统供应合同。
连接新加坡,马来西亚,缅甸,泰国和印度(孟买和金奈)。
“薄雾”:
总延伸距离约为8,100公里,
采用最新的光波分复用传输系统,
设计容量超过每秒216Tbps。
该电缆的目标是在2022年底完成。
新闻发布| NEC
https://jpn.nec.com/press/202008/20200821_02.html
Orient Link Pte. Ltd. (OLL) and NEC Corporation (NEC)
Tokyo & Singapore, August 21, 2020 –
announced that they have signed an agreement to build the MIST Cable System (MIST). MIST will directly connect
Singapore,
Malaysia,
Myanmar,
Thailand 、
India (Mumbai and Chennai)
deliver a design capacity of more than 216 terabits per second (Tbps).
Construction of the nearly 8,100-kilometer optical submarine cable
is targeted to be completed by the third quarter of FY2022.
Overview of MIST Submarine Cable
Name MIST (Myanmar/Malaysia India Singapore Transit)
Total design capacity More than 216 Tbps / 12FP
Total cable length Approx. 8,100Km
Landing points Singapore, Malaysia, Myanmar, Thailand, India (Mumbai and Chennai)
Investment Approx. 400M-USD
Operational Launch 3Q FY2022
NEC
https://www.nec.com/en/press/202008/global_20200821_02.html
Home – Orient Link “Here to Support the Growing Demand for International Data.”